The same swap, with weights on, moves sum w C by w_a p_b − w_b p_a. That is negative exactly when p_a / w_a > p_b / w_b, so the ordering key is the ratio and not the time and not the weight. The two rules that use one number each are both wrong, and on the lab's instance running the heaviest job first costs 113 where the ratio reaches 97.

swap adjacent a then b: sum w C moves by w_a p_b − w_b p_a negative ⟺ w_a p_b < w_b p_a ⟺ p_a / w_a > p_b / w_b WSPT (Smith): sort by p/w ASCENDING ties give the same sum w C A 3:1, B 8:4, C 2:3, D 6:2 ratios 3, 2, 2/3, 3 WSPT C B A D 97 heaviest-first B C D A 113 shortest-first C A D B 109 equal weights ⟹ p/w is p rescaled ⟹ Smith’s rule collapses to SPT
The same exchange, one multiplication heavier

Core ideas

What this lesson establishes

One new subtraction and two corollaries, one of which is that the two rules a reader would guess are both beaten on the same instance.

1

The weighted swap is the unweighted swap with two multiplications

Only C_a and C_b move, exactly as before, so the change in sum w C is w_a C_a + w_b C_b after minus before. Substituting the four completion times and cancelling the start time gives w_a p_b − w_b p_a. Nothing about the derivation changed; the objective put a multiplier on each term and the multiplier survived into the answer.

2

The condition is a ratio, so neither number decides alone

w_a p_b < w_b p_a divides through by w_a w_b, which is positive, to give p_a / w_a < p_b / w_b. So the swap improves exactly when the job in front has the larger ratio, and the rule is to sort by p/w ascending. A long heavy job and a short light job can have the same ratio, in which case the order between them does not matter at all: the difference is exactly zero.

3

Both one-number rules lose, and they lose differently

Heaviest-weight-first ignores p and puts an eight-hour job at the front because it is worth four; shortest-first ignores w and puts a nearly worthless job at the front because it takes two hours. On the lab's instance they cost 113 and 109 against the ratio's 97. Neither is a silly rule; each is a correct rule for a question nobody asked.

The material

Weights, the ratio, and two plausible rules that lose

The subtraction with weights in it, the rule it produces, and a measured comparison against the two rules a reader would reach for first.

Definition · Weighted completion time

Each job carries a positive weight w_j, and the objective is sum w C = sum over j of w_j C_j. The weight is the cost of one unit of waiting for that job: twice the weight means an hour of delay hurts twice as much. Weights are not priorities and they are not ranks — they are multipliers, and the arithmetic uses their sizes.

Theorem · The weighted exchange identity

Let a and b be adjacent with a first. Swapping them changes sum w C by exactly w_a p_b − w_b p_a, whatever the start time and whatever the rest of the order.

Only C_a and C_b change, for the same reason as in the unweighted case: earlier jobs are untouched, and later jobs start once the same two jobs have been done.

Let the pair start at t. Before, the two contribute w_a(t + p_a) + w_b(t + p_a + p_b). After, they contribute w_b(t + p_b) + w_a(t + p_b + p_a).

Subtracting, every term in t cancels, w_a p_a cancels against itself and w_b p_b against itself, and what is left is w_a p_b − w_b p_a.

□

Divide the improvement condition w_a p_b − w_b p_a < 0 by the positive quantity w_a w_b and it becomes p_a / w_a > p_b / w_b. This is why the weights must be strictly positive and why the lab refuses a weight of zero rather than accepting it: the ratio is a division, and a job of no weight at all is a job whose position cannot be argued about by this method.

Definition · Smith's rule

The weighted shortest processing time rule, or Smith's rule, orders the jobs by p / w ascending. It minimises sum w C. With all the weights equal it is p divided by a constant, so it is shortest-first again — the unweighted theorem is the special case, not a separate result.

Four jobs, three rules, and two of them wrong

jobs A 3:1 B 8:4 C 2:3 D 6:2 p:w ratios A 3 B 2 C 2/3 D 3 typed A B C D sum wC 124 WEIGHT B C D A sum wC 113 heaviest weight first SPT C A D B sum wC 109 shortest time first WSPT C B A D sum wC 97 the ratio best of all 24 orders 97 attained twice: C B A D and C B D A makespan 19 in every one of them

B is both the longest job and the heaviest, which is what makes the instance worth looking at: the two one-number rules disagree about it as loudly as they can. Heaviest-first puts B at the very front, where its eight hours delay everything else. Shortest-first puts it at the very back, where four units of weight wait the whole nineteen hours. The ratio puts it second, and the 97 is not available any other way.

Example · The one swap that separates the two rules

Heaviest-first produces B C D A. The ratio of B is 2 and the ratio of C is 2/3, so the pair at the front is out of order and the identity says the swap moves w_B p_C − w_C p_B = 4 × 2 − 3 × 8 = 8 − 24 = −16.

Make that one swap and the order becomes C B D A, worth 113 − 16 = 97, which is optimal. So the entire gap between the rival rule and the theorem on this instance is one adjacent pair, and the exact size of the gap was available from two multiplications before the swap was made.

Where the walk from the typed order goes

start A B C D sum wC 124 1 swap A,B w_A p_B − w_B p_A = 1(8) − 4(3) = −4 120 2 swap A,C w_A p_C − w_C p_A = 1(2) − 3(3) = −7 113 3 swap B,C w_B p_C − w_C p_B = 4(2) − 3(8) = −16 97 stop C B A D sum wC 97 Smith’s own order the finished schedule, job by job C p 2 w 3 C 2 wC 6 B p 8 w 4 C 10 wC 40 A p 3 w 1 C 13 wC 13 D p 6 w 2 C 19 wC 38 97

Three swaps, three subtractions, and the walk stops on Smith's order without ever having been told what Smith's rule is. That is the same demonstration as in the unweighted case with one difference worth noticing: the largest single improvement, −16, came last. There is no reason for the improvements to get smaller, and a reader who stops swapping because the gains look small has stopped early.

The unweighted rule is not merely analogous to this one; it is this one. Set every weight to the same value w and the ratio p/w orders the jobs exactly as p does, so Smith's rule returns the shortest-first order and sum w C = w sum C is minimised by minimising sum C. The lab has a preset with four equal weights for exactly this check, and the two rules return the same order on it.

One warning about the ratio, because it is the kind of thing that survives into practice as folklore. p/w is an ordering key and nothing else. It is not a cost, it is not a priority score to be compared across instances, and adding the ratios up or averaging them computes nothing. The only fact about it is that sorting by it ascending minimises sum w C.

Interactive

Smith's rule, and the same exchange with weights on

The swap moves sum wC by w_a p_b − w_b p_a, which is negative exactly when p_a/w_a > p_b/w_b

Smith's rule, and the same exchange with weights onThe swap moves sum wC by w_a p_b − w_b p_a, which is negative exactly when p_a/w_a > p_b/w_b
the order you typedafter the swap, if it improvesafter the swap, if it does notthe rule's own order

Method

Sequencing when the jobs are not worth the same

Four steps, and the second is the one that separates this rule from the two that look like it.

1

Write each job as time and weight, and say what the weight means

p:w, with w the cost of one unit of waiting. If you cannot say what a weight of 4 means relative to a weight of 1 in the units of the problem, the model is not finished and no rule will finish it for you.

2

Compute p/w for every job, exactly

As a fraction. 2/3 and 2 and 3 are the keys on the lab's instance, and two jobs there tie at 3. Rounding the ratios to decimals is how a genuine tie becomes a fictitious ordering, and on a tie the exchange identity says the order genuinely does not matter.

3

Sort ascending by the ratio, not by either number

Smallest ratio first. Checking one pair by hand is worth the seconds it takes: on the lab's instance C has ratio 2/3 and B has 2, so C goes first even though B is four times the weight.

4

Check the result against the rival you were going to use

Run heaviest-weight-first on the same jobs and compute sum w C for both. On the lab's instance that is 113 against 97, and the difference is the number worth carrying into the argument about whether the rule is worth changing.

Ratios, rivals and the weighted subtraction

Score 0 / 0

Four jobs where the heaviest is also the longest

The lab's opening preset. B is eight hours long and worth four, so the two one-number rules put it at opposite ends of the schedule and the ratio puts it in the middle.

jobs A 3:1 B 8:4 C 2:3 D 6:2 ratios A 3 B 2 C 2/3 D 3 SMITH’S ORDER, by ratio ascending C (2/3), B (2), A (3), D (3) job p w C wC C 2 3 2 6 B 8 4 10 40 A 3 1 13 13 D 6 2 19 38 97 A and D tie at 3, so C B D A is also worth 97 — 2 of the 24 orders attain it HEAVIEST WEIGHT FIRST B C D A sum wC 113 one swap at the front: w_B p_C − w_C p_B = 4(2) − 3(8) = −16 113 − 16 = 97, and the order is C B D A SHORTEST TIME FIRST C A D B sum wC 109 (sum C 37, which IS optimal) THE WALK FROM THE TYPED ORDER A B C D, worth 124 swap A,B 1(8) − 4(3) = −4 120 swap A,C 1(2) − 3(3) = −7 113 swap B,C 4(2) − 3(8) = −16 97 three swaps, and it stops

The line to keep is the one about shortest-first: it attains sum C = 37, which is the true optimum for the unweighted objective, and it costs 109 on the weighted one. A rule can be exactly, provably optimal and be the wrong rule, and there is nothing in its output that reveals which of the two it is being.

The tie between A and D at ratio 3 is worth checking by hand. A is 3:1 and D is 6:2; the swap moves w_A p_D − w_D p_A = 1(6) − 2(3) = 0. Two of the twenty-four orders attain 97, and the lab reports the count rather than naming one order and implying it is unique.

For a rehearsal, type the five jobs of “One Machine, Six Objectives” in as p:w — A 6:1, B 4:2, C 5:4, D 3:3, E 7:1 — and work out the three figures before the panel does. The supplied first move is that the ratios are 6, 2, 5/4, 1, 7. Smith's rule gives 108, heaviest-first gives 111 and shortest-first gives 114; one adjacent swap separates the shortest-first order from Smith's, and it is worth −6.

Common mistakes

1
Sorting by the weight, or by the time, and calling it a priority ruleEach ignores half of the data. On the lab's instance heaviest-first costs 113 and shortest-first 109 where 97 is available, and shortest-first is simultaneously optimal for the unweighted objective. The ratio is not a compromise between the two rules; it is the condition the subtraction produced.
2
Rounding the ratios2/3, 2, 3 and 3 are exact. Two jobs tie here and the identity says their order moves sum w C by exactly zero; a decimal ratio invents a difference between them and hides the fact that two of the twenty-four orders attain the optimum. Every figure on this path is a fraction for reasons of exactly this kind.
3
Treating p/w as a score with meaning of its ownIt is an ordering key. Adding the ratios, averaging them, comparing them between instances or reporting one as a job's priority computes nothing. The only theorem is that sorting ascending by it minimises sum w C, and it says nothing about any other objective — Smith's order costs 66 on sum C where 65 was available on the instance of “One Machine, Six Objectives”.

Check your understanding

✓
Finish when you can derive the ratio rule from the swap rather than recalling it.

You should be able to run the adjacent exchange with weights, reach w_a p_b − w_b p_a, divide by w_a w_b to turn the improvement condition into p_a/w_a > p_b/w_b, state Smith's rule, show that equal weights reduce it to shortest-first, and compute by how much a named rival rule loses on a given instance rather than asserting that it does.

Note: Both rules so far minimise a total, and a total is forgiving: one job finishing very late can be paid for by four finishing early. Due dates are not like that. The next objective takes a maximum rather than a sum, so one bad job sets the whole figure, and the exchange argument that proves the rule for it has to compare two maxima rather than two sums. “Earliest Due Date and Maximum Lateness” runs it, and then shows the same order losing on the objective a reader will assume it also solves.

Kept in this browser only, for you. Nothing is sent anywhere and nothing checks it. Carry it to another device.

Feedback and recommendations

Something to change about this lesson? Write it down, tick it off when it is handled, and export the list when you want to act on it. Kept in this browser only: nothing is sent anywhere, and nobody is notified.

No recommendations yet for this lesson.