Scheduling

This is the course on this path with no matrix in it. Five jobs on one machine have 120 orders and six reasonable objectives, and the order that wins on one of them is beaten on the others by a different order each time — so the first thing here is that a schedule is not good, it is good at something. The rules that follow are all proved the same way and none of them needs calculus: take two jobs standing next to each other, swap them, and compute the exact quantity the swap moved. That one subtraction gives shortest-processing-time, Smith’s ratio and earliest-due-date, and it is honest about the two places it does not reach. Then the machine count goes up: two in series still has an exact rule, m in parallel has a heuristic with a bound proved from two lower bounds, and a shop where each job has its own route has neither — one binary choice per shared machine, and some combinations of those choices describe no schedule at all.

one machine, all ready at 0, no idle: makespan = sum p, the SAME in any order swap adjacent a then b: sum C moves by p_b − p_a, sum wC by w_a p_b − w_b p_a SPT minimises sum C WSPT (p/w ascending) minimises sum wC EDD minimises L max and T max, and does NOT minimise sum T or the late count Moore–Hodgson: offer in due-date order, discard the LONGEST accepted job Johnson: p1 < p2 to the front by p1 up, the rest to the back by p2 down m machines: makespan ≥ sum p / m and ≥ max p; LPT within 4/3 − 1/(3m) crashing: min sum rate·y, the deadline as ONE right-hand side; a convex curve
What this course is about
Subject
Operations Research
Lessons
9
Format
Interactive

Overview

What you will be able to do

By the end you can say which of six objectives a schedule is being judged on and which one it cannot affect, prove a sequencing rule by swapping two neighbours rather than quoting it, run an algorithm whose discard is not the job that went wrong, bound a parallel-machine schedule from below before building one, and price a deadline exactly and then check the plan with a method that is not the programme that produced it.

1

Score one order against every objective at once

Completion times, weighted completion times, lateness, tardiness and the late count off a single clock; the makespan shown to be sum p in every order; and each figure compared with the best of all n! orders rather than asserted.

2

Prove a sequencing rule by adjacent exchange

The swap identity p_b − p_a for total completion time and w_a p_b − w_b p_a for the weighted version, derived with a symbolic start time that cancels, the improvement condition read off the sign, and the rule obtained as the orders no swap improves.

3

Beat the rules that use one number

Heaviest-weight-first and shortest-first measured against Smith's ratio on the same data, with the size of the gap accounted for by named adjacent swaps rather than asserted as a general property.

4

Meet due dates, and name the question you answered

Earliest-due-date proved optimal for maximum lateness by an exchange over a maximum, then measured on total tardiness and on the late count, where it is beaten; Moore–Hodgson run step by step for the count; and 1 || sum T named as the boundary the technique does not reach.

5

Schedule more than one machine, with a bound

Johnson's rule for two machines in series, with the makespan accounted for as second-machine work plus second-machine idle; longest-first on m identical machines against both lower bounds and against the best assignment there is; and a job shop as one binary choice per shared pair, with the deadlocked combinations counted as answers.

6

Price a deadline and verify the plan

The crashing programme with the deadline as a single right-hand side, the exact convex time-cost curve from ranging that row, and the durations it buys put back through a forward and a backward pass that share no arithmetic with the simplex.

Lessons

9 lessons

The objectives first, because a reader who has not watched one order win once and lose five times will keep asking whether a schedule is good; then the adjacent exchange twice, unweighted and weighted, because it is the whole proof technique and the second use of it is the first with one multiplication added; then the two due-date questions, which sound like one question and have different answers, with the one that has no rule named rather than approximated. After that the machine count rises, and each rise costs something: two machines in series keeps an exact rule, m in parallel keeps a guarantee, a job shop keeps neither. The last lesson changes what is being spent.

One Machine, Six ObjectivesRun five jobs in the order they arrived, score that order against six objectives at once, and find it is best at none of them.Not marked
Shortest Processing Time and the Adjacent ExchangeSwap two neighbouring jobs, watch the total completion time move by one subtraction, and let the swaps walk you from the worst order to the best.Not marked
Smith's Rule and Weighted Completion TimePut a weight on each job, run the same exchange, and the ordering key becomes the ratio p/w rather than either number on its own.Not marked
Earliest Due Date and Maximum LatenessEarliest-due-date minimises the worst lateness, by the same exchange; on the same five jobs it is beaten on total tardiness and leaves twice as many jobs late as it needs to.Not marked
Minimising the Number of Late JobsOffer the jobs in due-date order, and whenever the accepted set runs past a due date throw out the longest job accepted so far, not the one that went late.Not marked
Two Machines in Series and Johnson's RuleEvery job goes through machine one then machine two; the makespan is now worth optimising, and it is machine two's idle time that the rule attacks.Not marked
Machines in Parallel, and What LPT GuaranteesPlace the longest jobs first on whichever machine is free soonest, and the answer is not optimal — it is within a factor that is proved from two lower bounds.Not marked
The Job Shop and Disjunctive OrientationsEach job visits the machines in its own order; every pair of operations sharing a machine is one binary choice, and some choices produce a schedule that deadlocks.Not marked
Crashing a Project and the Time-Cost CurveEach activity can be shortened at a price; the cheapest way to meet a deadline is a linear programme, and the deadline is one right-hand side.Not marked

Recommended background

Linear programming models and duality and sensitivity analysis from this path — right-hand-side ranging in particular, because the exact time-cost curve is that machinery applied to a deadline row and not a second implementation of anything; networks: flows, paths and assignments, for the project network and the critical path, which the last two lessons use as a tool rather than rebuild; and integer programming, for the either-or constraint, which is exactly what a pair of operations sharing a machine is; from discrete mathematics, searching and sorting, greedy algorithms and the exchange arguments behind them, paths and connectivity for the cycle that is a deadlock, and P, NP and NP-completeness, because three of the models here are hard and the course says so rather than offering a rule; and from algebra, inequalities and the arithmetic of ratios.

Practice suggestions

Write the objective at the top of the page before choosing a rule. Every theorem on this course names one objective and is silent about the other five, and the rules disagree: shortest-first is optimal for total completion time and costs 114 on the weighted version where 108 is available from a rule that is no harder to run.

Prove a rule by swapping two neighbours and writing one subtraction. Give the pair a symbolic start time, write both schedules' completion times, subtract, and check that the start time cancelled. If the difference still mentions another job or the clock, the objective has no exchange rule and the right move is to say so.

Whenever a rule wins, measure what it cost elsewhere. Earliest-due-date attains the best maximum lateness on the lab's five jobs and leaves four jobs late where two is possible. Both sentences are true, both are about due dates, and a report that states only the first is misleading without containing a falsehood.

On more than one machine, compute a lower bound before building a schedule. Total work over the machine count and the longest single job are both free, and a schedule that attains the larger of them is proved optimal with no search at all — while a schedule that does not tells you how much of the remaining gap you have actually bounded.

What it does not cover

Release dates and preemption. Every job here is available at time zero and runs to completion, and that is not a simplification of the proofs — it is a condition on them. Release dates change which exchanges are legal and interrupts change what a schedule is, and nothing proved on this course survives either.

An algorithm for total tardiness. 1 || sum T has no adjacent-exchange rule, the labs exhibit its optimum by enumeration on small instances, and the course names it as the boundary of the technique. Offering a plausible heuristic here would teach the opposite of everything before it.

Anything random, and anything arriving over time. Durations are known numbers, the work is all present at the start, and no machine breaks down. Queues with arrivals and service times as distributions are “Markov Chains, Decisions and Queues”, and a schedule evaluated under uncertainty is “Simulation and Variance Reduction”.

Resource-constrained project scheduling. The crashing programme assumes the activities are independent, so two of them can be shortened at once without competing for the same people. Adding a resource pool turns the timing rows into disjunctions and makes the project network an integer programme, which is a real subject and not a variant of this one.

The job shop at any interesting scale. Enumerating 2^k orientations is exact and is a teaching device; what survives is branch and bound on the same binary choices, which is “Integer Programming”, plus the shifting-bottleneck and local-search methods built on top of it, which are named here and nowhere developed.

The results this course cites and does not prove. The 4/3 − 1/(3m) guarantee for longest-first on identical machines is stated and measured against, never derived; the NP-hardness of 1 || sum T, of makespan on identical machines and of the three-machine flow shop and the job shop are taken from “Algorithms and Complexity”; and the special case in which a three-machine flow shop reduces to two is named without its condition being worked. Each is stated where it is needed, with its owner named.